A power project with signed financing documents cannot yet supply a household. Uganda’s National Energy Compact makes that distinction explicit, separating infrastructure intended to operate by the end of 2030 from projects expected to secure financing by then and start producing power later.
That separation is central to reading the country’s energy ambitions accurately. The official compact sets headline goals of 85% electricity access and 50% access to modern cooking solutions by 2030. These are targets, not achieved coverage.

Two project lists, two different milestones
The document identifies an operational generation fleet of roughly 2,500 megawatts under Category A. Category B covers another approximately 5,800 megawatts reaching financial close by the end of 2030, with commercial operation afterward. Combining those figures into a claim that all the capacity will be generating electricity in 2030 would erase the compact’s own distinction.
The plan also seeks about $9.4 billion in additional private capital over 2026–2030. That is an ambition to mobilise financing, rather than money already received. A project can move through feasibility work, procurement, financing and construction at different speeds.
For readers, the practical lesson is to attach a verb to every large number. Is a plant proposed, licensed, financed, under construction, commissioned or delivering usable electricity? Each stage is meaningful, but each answers a different question.
Access extends beyond generation
The World Bank’s official directory lists Uganda’s compact under June 2026. The country plans sit within Mission 300, the joint World Bank and African Development Bank effort to expand electricity access across Africa.
A national compact brings generation together with networks, last-mile connections, finance and utility performance. Those elements cannot substitute for one another. More generation does little for an unconnected household if the local distribution line is absent. A new connection is less useful to a workshop if power quality cannot support its equipment.
In an illustrative rural trading centre, different customers could require different services. Lighting and phone charging have one demand profile; milling grain, welding or keeping produce cold have another. A project’s design needs to identify the intended service before describing how many people it will benefit.
This also explains why stand-alone solar, mini-grids and conventional grid expansion should be judged against the work they can support. The relevant comparison includes reliability, capacity, maintenance and the customer’s total cost over time.
Cooking needs its own measurement
The Mission 300 FAQ distinguishes its core electricity-access metric from clean-cooking priorities. The electricity measure counts people receiving first-time access through verified household connections. A cooking target should therefore be tracked separately rather than added to a connection total.
That is more than an accounting detail. Owning an appliance, being able to obtain its fuel and using it consistently are different outcomes. A household may continue using several cooking methods because of price, availability or the foods being prepared. A useful evaluation would examine the service actually used, not only the equipment distributed.
There is similar value in publishing the definition behind an access figure. The compact contains differing subsidiary access references in different sections. The headline commitment is clear, but readers should avoid manufacturing a single reconciled baseline from inconsistent passages without clarification from the authorities.
What would make delivery visible?
A credible progress report could separate new connections, service reliability, operating capacity and financing milestones. It could also identify which projects changed category and explain delays or revised costs. These are suggested ways of reading delivery evidence, not a claim that every measure is already publicly available.
For businesses, a connection announcement should eventually translate into predictable operating hours and a bill they can plan around. For households, it should mean a service that remains affordable and repairable. For the public, it should be possible to distinguish commitments from completed assets.
Uganda’s compact offers a useful structure for asking those questions. Its most revealing feature is the explicit boundary between a plant operating and a project financed for later construction. Keeping that boundary intact will make future energy headlines more informative as the country works toward its 2030 goals.